4 weeks to build a 100 m² raw earth floor slab

These old stables had been waiting 25 years for renovation. The trigger? A family wedding scheduled in… 4 weeks. In this context of absolute challenge, CARTDESIGN took on the realisation of a 100 m² raw earth floor slab — from soil preparation to welcoming 100 guests.

The construction steps

  • Test samples & mix trials — Three different mixes tested in advance to find the ideal composition of earth / sand / aggregates for this specific base.
  • Excavation — Earthworks and levelling of the former stable floor.
  • Ventilated rubble base with conduits — Installation of the ventilated gravel bed incorporating conduits for water and electricity.
  • Expanded cork insulation (2×4 cm) — To break the thermal bridge with the cold ground.
  • Underfloor heating — Circuit embedded in the slab mass.
  • Placement of approximately 25 tonnes of material — Mix of sand, clay, stones and rubble, mixed on site in a mixer.
  • Finishing & drying — Surface work and drying during a period of intense heat — both a constraint and a stroke of luck.

The project in pictures

Test samples with different mix types — 18 May 2025
18 May 2025 — Test samples with different mix types
Excavation — 19 May 2025
19 May 2025 — Excavation
Ventilated rubble base with conduits — 25 May 2025
25 May 2025 — Ventilated rubble base with conduits for water and electricity
Ventilated rubble base — 27 May 2025
27 May 2025 — Ventilated rubble base
2×4 cm expanded cork with underfloor heating — 29 May 2025
29 May 2025 — 2×4 cm expanded cork with underfloor heating
Sand, clay, stones — 30 May 2025
30 May 2025 — Sand — Clay — Stones
Adding rubble to the mixer — 31 May 2025
31 May 2025 — Adding rubble to the mixer
Placing the material — 1 June 2025
1 June 2025 — Placing the material
100 guests on the slab — 28 June 2025
28 June 2025 — 100 guests on the slab

The result: 100 guests, meals, dancing — and a slab that held

The timing was tight right up until the last moment. The heatwave conditions of June were, paradoxically, our greatest ally in accelerating the drying of the slab. 100 guests, meals, dancing — not a single incident. Most guests didn't even realise they were walking on a raw earth floor.

This project proved to us, once again, that earth construction is fully compatible with demanding timing and performance constraints. Raw earth is not a fragile material reserved for experimental projects: it is a robust, living material built for the reality of real construction sites.

A true technical demonstration — and a call to institutions

It is more than time for Buildwise to make a genuine commitment to innovation that matters. In a context where sustainability has become a central challenge, the absence of accessible technical data sheets or recommendations on plant-based fibres or raw earth raises serious questions.

How can we continue to ignore these materials, when many professionals in the sector use them every day? How can this gap be justified, when so many of us are compelled to be affiliated with this institution, without it being able to provide us with technical support?

Let us activate every actor within our reach to drive a real transition, now.

Thanks to CRAterre and amàco for the inspiration.